BOI Promotion Procedure
Processes for Projects Application and Utilization
Action Required after a Project is Approved for Promotion
After receipt of the investment promotion certificate, the promoted company must meet the
following conditions and inform the OBOI at each stage
- Within 30 months, the machinery and
equipment must be imported to benefit from the reduction of, or exemption
from, taxes and duties.
- Within 36 months, construction
must be completed, the machinery and equipment installed, and the factory
ready to begin operations. Use form F PM OP 01.
- The promoted company must ask for
written permission from the OBOI if the operation has to be halted for
more than two months.
- The OBOI must give written
permission before a promoted company may mortgage, sell, transfer, or rent
machinery which was brought into the country either exempt from, or at a
reduced rate of tax. Similar permission must be obtained to use machinery
for non-approved purposes.
- If an inspector finds that
the promoted company is not meeting the prescribed conditions, the OBOI
will send an official warning note. If there are insufficient reasons why
the conditions are not being met, the OBOI will recommend to the Board
that the promotion certificate be withdrawn, and inform the Ministry of
Finance and other related agencies accordingly.